Kachina Trail Reconstruction Project

CivicSend Slideshow Left Arrow Slideshow Right Arrow

What's New...

 
5/19/17: 
Work on the remaining new sewer system was completed on Thursday and the detour around the construction zone will be removed Friday evening. The County’s contractor was delayed from completing this project for two weeks due to soil instability that was unexpectedly encountered by crews working 20+ feet below grade on the last 100 feet of the project at the intersection of Kachina Trail and Kachina Boulevard. Soil instability at this depth, which is very difficult to assess prior to a project’s groundbreaking, posed serious safety issues during the deep trench work for the new sewer lines and laterals. Crews are currently installing a temporary all-weather surface along Kachina Trail that will be in place when the Kachina Trail Pavement Reconstruction Project starts early next month. Final work on the project, which includes the switchover to the new sewer system, is scheduled to be completed next Tuesday, weather permitting.  

The contract for the Arizona Department of Transportation (ADOT)-managed Kachina Trail Reconstruction Project will be awarded at the State Transportation Board meeting today. Crews are expected to mobilize for construction during the week of June 5.   

Project Overview


The Kachina Trail Utility Relocation Project is necessary to address the community's aging utility infrastructure, which is almost 50 years old. It also is critical to complete this utility relocation work so that the ADOT-Managed Kachina Trail Reconstruction Project can break ground next month and be completed by the fall.

Utility Relocation Work Start: September 2016
Utility Relocation Work - Estimated Completion: May 19, 2017
Project Contractor: Tiffany Construction Co.
Project Engineer: Civiltec Engineering Inc. ***************************************************
Kachina Trail Reconstruction - Estimated Project Start: Summer 2017
Status: In Engineering
Project Contractor: TBD
Project Engineer: TBD
Estimated Construction Cost: $2.2 Million