Burris Lane Drainage & Road Improvement Project

What's New... 
   
07/13/2018: 
Mainline paving operations were completed this afternoon for the Burris Lane Drainage & Road Improvement Project. Crews installed more than 12,000 tons of asphalt just today, which completed the new 3.5-inch asphalt layer along Burris Lane.

Tiffany Construction Co. is working daily between 7:00 a.m. and 5:00 p.m., Monday through Friday with some weekend work possible. Flaggers, signage and other traffic control devices are in place as needed to direct vehicles through the construction zone. This schedule is subject to change based on weather and other unforeseen factors.

March 14 Community Meeting Materials:

Meeting Presentation

Project Cross Section

Project Area Roll Plot

Project Overview

The Burris Lane Drainage & Road Improvement Project is necessary to improve and extend the service life of Burris Lane. Funded entirely by Prop. 403, this project includes utility relocation, localized drainage improvements, pavement rehabilitation and installation of widened shoulders for multimodal use.

Status: Under Construction
Construction Start: April 23, 2018
Est. Completion: Fall 2018 

Project Contractor: Tiffany Construction
Project Engineer: Kimley-Horn
Offsite Drainage Engineer: Civiltec Engineering Inc.

Est. Construction Cost: $2.4 Million