Kachina Village Projects

Kachina Trail Emergency Guardrail & Roadside Drainage Repair Project (2022)

Project Overview

The Kachina Trail Emergency Guardrail & Roadside Drainage Repair Project included the repair and replacement of damaged guardrail and roadside drainage infrastructure along the section of Kachina Trail located about 0.2 miles north of Kona Trail. This project wasnecessary because the damaged guardrail does not meet current safety standards and the compromised roadside drainage is causing undercutting erosion along the edge of the roadway. Detour information for this project is available above.

The project is scheduled for completion in early July. However, this schedule is subject to change due to weather or other unforeseen factors. 

  • Status: Completed
  • Construction Start: June 20, 2022
  • Construction Completion: July 22 2022
  • Project Cost: $134,430.00
  • Project Contractor: McCauley Construction, Inc.

Ancient Trail Reconstruction Project: Tonalea Trail to Kachina Trail (2022)

Project Overview

The Ancient Trail Reconstruction Project included the replacement of 0.52 miles of pavement on Ancient Trail between Tonalea Trail  and Kachina Trail.  Replacing the asphalt extends roadway life, increases rideability, and reduces maintenance costs. Funded entirely by Prop. 403, this project also includes shoulder widening and drainage improvements along this stretch of roadway.

  • Status: Completed
  • Project Designer: Turner Engineering, Inc.
  • Construction Start: May 23, 2022
  • Construction Completion: July 29 2022
  • Project Cost: $1,287,935.52
  • Project Contractor: J. Banicki Construction, Inc.

Kachina Trail Road Reconstruction Project (2021)

Project Overview

  • Status: Completed
  • Construction Start: August 2021
  • Completion: October 2021
  • Project Cost: $903,000
  • Project Contractor: Tiffany Construction Co.

The Kachina Trail Reconstruction Project included the replacement of 0.35 miles of pavement on Kachina Trail between Ancient Trail and Kona Trail. Replacing the asphalt extends roadway life, increases rideability, and reduces maintenance costs. In addition, the project includes installation of cinder management measures (aka "Stormceptors") to reduce the amount of cinders flowing into Pumphouse Wash.

  • Status: Approaching Completed
  • Construction Start: August 2021
  • Completion: October 2021
  • Project Cost: $903,000
  • Project Contractor: Tiffany Construction Co.

Chaco Trail Drainage Improvement Project (2021) 

Project Overview

The Chaco Trail Drainage Improvement Project replaces an existing drop inlet structure on Chaco Trail in Kachina Village, which was undersized to meet demand. In addition, a second drop inlet structure and a connecting pipe were be installed with surface repairs made to the existing concrete swale in order to better facilitate roadway drainage away from residential structures.

  • Status: Completed
  • Construction Start: November 8 2021
  • Completion: November 19 2021 

Kachina Trail Utility Relocation & Reconstruction Project (2017)

Project Overview

The Kachina Trail Utility Relocation & Reconstruction Project included reconstruction of the roadway, widening shoulders for multimodal use, utility relocation and the removal of the median on Kachina Trail from the intersection with Kachina Boulevard to the bridge near Ancient Trail.

Status: Completed

Project Cost: $1,600,000

Project Engineer - Utility Relocation:  Civiltec Engineering Inc.

Project Engineer - Road Reconstruction: Dibble Engineering