Kachina Village Projects

Kachina Village Snow Day School Bus Stop Project

What's New...

November 21, 2020: Construction on the Kachina Village Snow Day School Bus Stop Project was substantially completed this week. The contractor and inspectors conducted a walkthrough of the project to determine remaining punch list items. Next week’s closeout work will include hydroseeding of affected area, gate installation, cleanup and demobilization.

Located on the County-owned parcel directly east of the Dollar General Store and adjacent to Raymond County Park, the Kachina Village Snow Day School Bus Stop Project will provide a site that will allow students to wait for the bus and for school buses to pull in from and out onto Tovar Trail more safely when snow prevents access to Kachina Village. This new school bus site will only be used when snowstorms or icing of roads cause accessibility issues within Kachina Village for school buses.  

  • Status: Under Construction
  • Construction Start: October 19, 2020
  • Completion: November 25, 2020
  • Est. Project Cost: $220,000
  • Project Contractor: Rummel Construction

Kachina Trail Sewer Line Repair Project

What's New...

September 18, 2020:  The Kachina Trail Sewer Line Repair Project was completed this week ahead of schedule. Thanks to everyone for their patience!

Project Overview

The Kachina Trail Sewer Line Repair Project was necessary to repair a broken service connection located near the centerline portion of Kachina Trail near the Dollar General Store. As a result of this fracture, fine-grain sediment and water seeped into the pipe, which caused a localized depression in the area. 

  • Status: Completed
  • Construction Start: September 8 2020
  • Completion: September 15 2020
  • Est. Project Cost: $66,000
  • Project Contractor: Tiffany Construction Co.