Kaibab Estates West Drainage Improvement Project

What's New...

December 30 2022: The Kaibab Estates West Drainage Improvement Project is slated to go out to bid in Winter 2023 

Project Overview

The Kaibab Estates West Drainage Improvement Project includes and roadside ditch improvements along Cumberland Road and Ann Lane, as well as the the replacement of an existing 18-inch culvert with two new 35-inch x 24-inch arch pipe culverts on Cumberland Road. This project is intended to improve drainage conveyance and help mitigate seasonal flooding impacts that occur in the drainages along Cumberland Rd and Ann Lane.

  • Status: Design Complete/Pre-Bid
  • Estimated Construction Start: Winter/Spring 2023
  • Estimated Completion: Spring 2023
  • Project Engineer: JE Fuller
  • Project Contractor: TBD
  • Estimated Construction Cost: $116,519