Lake Mary Road Mill & Fill Project: Phase 1

What's New...

06 October 2023: 

  • This week’s work on the substantially completed Lake Mary Road Mill & Fill Project: Phase 1 included fog sealing & restriping.

Project Overview

The Lake Mary Road Mill & Fill Project: Phase 1 included the milling of existing pavement and the subsequent installation of 1.5” Polymer Modified Asphalt Concrete from the City of Flagstaff city limits south to approximately Milepost (MP) 333. Approximately 5.3 miles of Lake Mary Road was milled and filled and then restriped. The project only treated the travel lanes.

  • Status: Substantial Completion
  • Construction Start: 10 July 2023
  • Substantial Completion: 04 August 2023
  • Project Engineer: Coconino County Public Works
  • Project Contractor: C & E Paving & Grading
  • Estimated Construction Cost: $1.95 million
  • Project Start Press Release