20 October 2023:
This week’s work on the substantially completed Kona Trail Pavement Rehabilitation: Kachina Trail to Bird Springs Ovi Project included completion of final punch list items and project demobilization. The project has been completed.
Project Overview
The Kona Trail Pavement Rehabilitation: Kachina Trail to Bird Springs Ovi Project includes a 2-inch pavement mill & fill of Kona Trail from Kachina Trail to Bird Springs Ovi (Approximately 1,500 ft). Work shall also include construction of a 2-foot-wide roadway shoulder build-up with recycled millings, damaged sidewalk panel replacement, curb ramp replacement, damaged concrete headwall replacement, and guardrail installation.