Lake Mary Road Mill & Fill Project: Phase 2

What's New...

22 September 2023: No work was conducted this week on the substantially completed Lake Mary Road Mill & Fill Project: Phase 2. No activity is scheduled for next week.

Project Overview

The Lake Mary Road Mill & Fill Project: Phase 2 includes the milling of existing pavement and the subsequent installation of 1.5” Polymer Modified Asphalt Concrete from the City of Flagstaff city limits south to approximately Milepost (MP) 333. Approximately 5.3 miles of Lake Mary Road was milled and filled and then restriped. The project only treated the travel lanes.

  • Status: Preconstruction
  • Estimated Construction Start: October 2023
  • Estimate Construction Completion: November 2023
  • Project Engineer: Coconino County Public Works
  • Project Contractor: C & E Paving & Grading
  • Estimated Construction Cost: TBD
  • Project Start Press Release